What is an advantage of applying the 'learn from experience' principle?

What is an advantage of applying the 'learn from experience' principle?

A.

It allows the project board to delegate cost tolerances to the project manager

B.

It allows the project team to fully understand their roles and responsibilities

C.

It allows the project manager to delegate time tolerances to the team managers

D.

It allows the project team to identify improvements to be made during the project