Which action should the project manager take during the 'assessing issues' step?
A.
Create an exception plan tor project board approval
B.
Gain project board feedback on the Issue priority
C.
Consider the impact of alternative options for resolution
D.
Determine the initial priority of the issue that has been raised
The Answer Is:
C
This question includes an explanation.
Explanation:
During the 'assessing issues' step, the project manager should consider the impact of alternative options for resolution. This involves evaluating different ways to address the issue, assessing their potential impacts on the project’s objectives, timescales, costs, and risks, and then proposing the most appropriate solution for decision by the project board.References: = PRINCE2® 7 Foundation handbook and online resources
Prince2-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"