Which is consistent with the eight guidance points of PRINCE2 Agile?
A.
The project manager role is NOT required when incorporating IT-only frameworks.
B.
The project manager role is NOT defined byScrum or Kanban.
C.
Working in an agile way removes the need for a project manager.
D.
A project manager is indicative of a 'command and control' culture.
The Answer Is:
B
This question includes an explanation.
Explanation:
This highlights that while Scrum and Kanban have their own roles and frameworks, the role of the project manager can still exist and be integrated within Agile practices, including PRINCE2 Agile.