Which is consistent with the eight guidance points of PRINCE2 Agile?

Which is consistent with the eight guidance points of PRINCE2 Agile?

A.

The project manager role is NOT required when incorporating IT-only frameworks.

B.

The project manager role is NOT defined byScrum or Kanban.

C.

Working in an agile way removes the need for a project manager.

D.

A project manager is indicative of a 'command and control' culture.