What is a purpose of the 'project closure' workshop?
A.
Align teams with project vision
B.
Create benefits management approach
C.
Update the project documentation
D.
Refine the release map for the next stage
The Answer Is:
C
This question includes an explanation.
Explanation:
The project closure workshop is held to formally close the project, during which project documentation is updated to reflect the final state of the project, lessons learned are captured, and approvals are obtained. This ensures that all activities are completed, the project has delivered its intended products, and knowledge is retained for future projects or organizational learning.
Aligning teams (A) and refining release maps (D) are activities conducted earlier in the lifecycle, while benefits management (B) is usually defined during initiation and planning stages.
[Reference: PRINCE2 Agile Foundation Version 2, Section 9.2 "Closing a Project," and PRINCE2 Agile Study Guide, Chapter 9., , ]
PRINCE2-Agile-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"