In which workshop are the project role descriptions created?
A.
Starting-up workshop
B.
Project kickoff workshop
C.
Project initiation workshop
D.
Project canvas workshop
The Answer Is:
A
This question includes an explanation.
Explanation:
The starting-up workshop is the initial workshop where the foundation for the project is established, including the creation and clarification of project role descriptions. Defining roles early ensures clarity of responsibilities, helps establish governance, and sets expectations for the project team.
Kickoff (B) focuses on launching the project, initiation (C) develops detailed plans, and the project canvas (D) is a tool for capturing high-level information but does not define roles explicitly.
[Reference: PRINCE2 Agile Foundation Version 2, Section 4.5 "Starting Up a Project," and PRINCE2 Agile Study Guide, Chapter 4., , ]
PRINCE2-Agile-Foundation PDF/Engine
Printable Format
Value of Money
100% Pass Assurance
Verified Answers
Researched by Industry Experts
Based on Real Exams Scenarios
100% Real Questions
Get 65% Discount on All Products,
Use Coupon: "ac4s65"