The risk register states that excavation may cause subsidence and damage nearby historic buildings.

The risk register states that excavation may cause subsidence and damage nearby historic buildings. The planned response is to survey the buildings and monitor vibration during excavation. The project executive is named as risk owner and the project manager as the sole risk action owner, even though operational specialists will perform the surveys and monitoring.

Is this an appropriate assignment, and why?

A.

Yes, because the project executive is sufficiently senior to own the risk and the project manager should coordinate every response action

B.

Yes, because the project executive should own risks that could affect business justification

C.

No, because the project manager must be both the risk owner and the risk action owner

D.

No, because the owner monitors the risk and the action owner implements the response

PRINCE2-7-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PRINCE2-7-Practitioner pdf
Get 80% Discount on All Products, Use Coupon: "BFDEAL80"