During initiation, the project executive asks the project manager to evaluate a credible business option...

During initiation, the project executive asks the project manager to evaluate a credible business option that omits the underground car park. The project manager includes an investment appraisal of that option in the full business case, despite the main contractor’s objection.

Is this an appropriate application of the business case practice, and why?

A.

Yes, because developing the business case includes comparing credible business options to select the most appropriate investment

B.

Yes, because customer and supplier organizations must always maintain completely separate project business cases regardless of the given investment

C.

No, because a requirement in the initial scope may never be tested as part of an alternative option

D.

No, because anticipated parking income means that no alternative should be assessed

PRINCE2-7-Practitioner PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PRINCE2-7-Practitioner pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"