While an iteration is in progress, a project manager notices a delay in the prototype.

While an iteration is in progress, a project manager notices a delay in the prototype. The sponsor reaches out to the project manager and suggests engaging with cross-functional stakeholders.

What should the project manager do?

A.

Analyze the delay and discuss the findings with the subject matter expert (SME).

B.

Ask the developers to discuss the delay at a retrospective.

C.

Request that the product owner assess whether the team needs an external subject matter expert (SME).

D.

Record this in the issue log and define further steps.