Throughout the project, the project manager consistently checks the work performance data and finds that...

Throughout the project, the project manager consistently checks the work performance data and finds that two stakeholders are not engaged in the project as expected. In addition, another stakeholder always complains that they are often involved in irrelevant meetings. What should the project manager do first?

A.

Communicate regularly with stakeholders and address issues.

B.

Perform a root cause analysis using the Ishikawa method.

C.

Review and update the stakeholder engagement plan.

D.

Remove those stakeholders from unwanted meetings.