Three testers joined the project team just before the end of the build.

Three testers joined the project team just before the end of the build. During the project team meeting, the testers indicated that the project quality is poor, and they should not continue testing until all the defects are fixed.

Which three actions should the project manager do? (Choose 3)

A.

Stop the project and review the output.

B.

Ask the testers to provide additional information.

C.

Ask the sponsor for assistance and guidance.

D.

Continue with testing according to the plan.

E.

Brainstorm the issue with the project team.