The project manager of an agile project has been asked to reduce the budget by...

The project manager of an agile project has been asked to reduce the budget by 30% Since this is a small project team, the budget is primarily allocated to resources

What strategy should the project manager use in order to keep delivering value in a restricted environment?

A.

Reduce the project staff and adjust the scope and timelines accordingly in support of the budget reduction.

B.

Balance the project team in order to accommodate the budget challenges, and provide training to mitigate the risk of low performance

C.

Prioritize the product backlog looking for high business value and low effort, and adjust the project budget and staffing to account for those items.

D.

Restrict the project scope only to basic critical features and run the project with the current staffing level until all of the budget is consumed

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"