The CFO has stated in a conversation with a project team member that they do...

The CFO has stated in a conversation with a project team member that they do not believe the project will be a success due to the high cost of implementation.

What should the project manager do?

A.

Meet with the CFO one-on-one to fully understand their cost concerns.

B.

Ask the project team to look for opportunities to cut project costs.

C.

Carry out a benefit analysis to present at the next project team meeting.

D.

Meet with the CFO and team to remind them of the project ' s key success measures.