Project stakeholders have provided a team with requirements that will take at least one year...

Project stakeholders have provided a team with requirements that will take at least one year to complete. The project sponsor advised that they need to see some return on investment (ROI) soon.

What should the project manager do?

A.

Request additional funding from the project sponsor to accelerate delivery.

B.

Discuss reducing the requirements with the project sponsor in order to release the product earlier.

C.

Prioritize the work into incremental features that can be delivered iteratively.

D.

Acknowledge that the benefits cannot be realized any sooner due to the nature of the requirements.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"