Phase 1 of a project has been implemented and moved into post-production support, while phase...

Phase 1 of a project has been implemented and moved into post-production support, while phase 2 development has started. During phase 1 closeout, team members are asked by the product manager to work on the phase 1 backlog items that are not in the approved requirements document. The team members complain that no one is in charge of production issues.

What two actions should the project manager take? (Choose 2)

A.

Discuss the backlog items with the product manager to determine what should be included as part of phase 2, and communicate the findings to the team.

B.

Review production support processes with the team, and request that the product manager take control over support issues going forward.

C.

Set up time to review the approved production support plan and associated processes with the business and team members.

D.

Reopen phase 1 to allow time for team members to wrap up issue resolutions for phase 1, and submit a change request to add backlog items to phase 2.

E.

Work with the business and product manager to determine any backlog items that should be reprioritized for inclusion in the next phase.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"