One of the main deliverables of a project is delayed due to a problem with...

One of the main deliverables of a project is delayed due to a problem with a key provider.

What should the project manager do?

A.

Discuss and create a project change request to replace the provider with a more responsible one from the provider list.

B.

Schedule a meeting with the provider to review any impacts to the project timeline and deliverables.

C.

Schedule a meeting with all relevant stakeholders to determine the best approach to resolve the issue.

D.

Discuss with the project sponsor and seek guidance to impose the penalty stipulated in the agreement.