In the middle of a software development project, the lead design programmer accepted an offer...

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?

A.

Consult the risk response plan.

B.

Assign the tasks to another team member.

C.

Update the resource calendar.

D.

Issue a request to the change control board (CCB).