In an agile product development environment, work is distributed to Cities A, B, andC, which...

In an agile product development environment, work is distributed to Cities A, B, and

C, which are geographically dispersed. The small teams work and collaborate to deliver the

sprints.

• City A's team focuses on the features of data capture.

• City B's team focuses on the user experience and development pieces.

• City C's team coordinates testing.

What should the project manager do to ensure a successful rollout of sprints?

A.

Ensure all three teams deliver independently without interactions so that they remain

focused and meet customer requirements.

B.

Implement communication techniques and ensure the teams follow a relay pattern of

handing off work from one team to the other.

C.

Use a fishbone analysis to resolve problems and iron out communication issues

between the teams.

D.

Maintain localized teams to circumvent the challenges of delay or any other

unforeseen risks that might prevent progress.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"