In a hybrid project a stakeholder requests some feature modifications directly to one of the...

In a hybrid project a stakeholder requests some feature modifications directly to one of the team members. When investigating further the project manager finds this to be a common practice m the business, which is different from what is stated in the project management plan

What should the project manager do?

A.

Update the risk register including noncompliance with the change process as a probable cause for scope creep

B.

Make sure that all stakeholders are aware and in agreement with the project governance structure m place

C.

Advise the team not to engage in modifications unless it follows the proper change approval process

D.

Escalate to the project management office (PMO) and request that the team member who accepted the request be replaced

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"