Weekend Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: ac4s65

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental...

Early in the execution phase, a project manager discovers that recent changes in enterprise environmental factors (EEFs) will severely reduce the implementation cost and shorten the project schedule. How should the project manager address this situation?

A.

Meet with the project team to decide how the remaining budget will be spent.

B.

Keep the extra budget as management reserve until project closeout

C.

Give the team extra time to finish tasks within the original timeline

D.

Follow the project escalation policy and communications management plan

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"