During the execution phase of a complex project, a key government stakeholder was replaced by a new representative from the same agency. During a project
meeting, the new stakeholder expressed complaints about not being informed of recent on-site changes. The stakeholder also said they would not have approved
these changes.
What should the project manager do first?