During the execution of a hybrid project, one developer had to be replaced.

During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much

experience in development.

What should the project manager do?

A.

Allow the team to reevaluate the tasks and determine how they should be allocated.

B.

Maintain the same task allocation structure to avoid any disruption in the project team.

C.

Move the developer to another team and look for a replacement developer.

D.

Request that all quality assurance tasks be allocated to the new resource.