During the daily standup meeting that is assessing progress against the current sprint, a team...

During the daily standup meeting that is assessing progress against the current sprint, a team member reports some delays due to a component

managed by an external vendor. How should the project manager address the team member's concern?

A.

Ask the team member to resolve the issue independently to minimize further delays.

B.

Ask the team member to provide details to address the issue with the vendor.

C.

Implement fast tracking to reduce the impact of the delay on the sprint.

D.

Update the communications management plan to prevent future reoccurrence.