During execution of the third sprint in a project, a project team is uncertain about...

During execution of the third sprint in a project, a project team is uncertain about the frequent updates on the vendor's platform. The team is concerned about how the updates will impact the rest of the backlog.

What should the project manager do to minimize the uncertainty?

A.

Speak with the vendor and explain that constant updates are impacting the project and request an action plan to minimize the changes.

B.

Schedule a spike meeting, conduct risk assessments, and incorporate them into the backlog to help with risk mitigation.

C.

Explain to the project team that the vendor's updates are something unpredictable, and the team must continue working on the project.

D.

Schedule a retrospective meeting and conduct a risk assessment with the team, implementing mitigation tasks before the next sprint.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"