During an agile team retrospective, a project team member mentions that the code quality is...

During an agile team retrospective, a project team member mentions that the code quality is degrading, which might result in future rework that

could become unmanageable with time. What should the project manager do?

A.

Help the team create the definition of done (DoD) to improve delivery quality.

B.

Add testing items to the backlog to assess quality periodically.

C.

Expand the team in order to improve the quality of the project.

D.

Compare the cost of improving quality against the cost of failure and adjust the budget.