Winter Sale Limited Time 60% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: 8w52ceb345

During a meeting with a customer, it was determined that participants of the meetinghad different...

During a meeting with a customer, it was determined that participants of the meeting

had different draft versions of an important design document. What should the project

manager do first to ensure that this does not happen again?

A.

Revisit the communication process control.

B.

Ensure only the approved version is shared.

C.

Investigate how draft versions were shared.

D.

Ensure only the latest version is shared.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 60% Discount on All Products, Use Coupon: "8w52ceb345"