During a kick-off meeting, the project manager notices that one of the stakeholders responsible for...

During a kick-off meeting, the project manager notices that one of the stakeholders responsible for providing key information to the team has a

low level of participation. This stakeholder believes that there will be no benefit from implementing the project. The project manager realizes that

this could be a high risk for the project.

Which action should the project manager take?

A.

Facilitate a supportive level of engagement for this stakeholder.

B.

Ask the project sponsor for advice as it might be possible to work with another stakeholder.

C.

Perform a qualitative risk analysis using a probability and impact matrix.

D.

Ensure the key information is accurate and monitor the situation as the project progresses.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"