Due to scope changes, some of the risks identified during the initiation phase have materialized...

Due to scope changes, some of the risks identified during the initiation phase have materialized into issues. What should the project manager do next?

A.

Submit a request to access contingency reserves and accept the changes.

B.

Submit a change request for additional resources and accept the changes.

C.

Ask the project sponsor to reject high-risk scope changes.

D.

Closely monitor scope changes and implement corrective actions.