Due to delays on some activities one of the project team members has increased the...

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

A.

Remove the changes to match the original requirements.

B.

Add team members to the project to avoid more schedule delays.

C.

Evaluate the impacts of the changes that were made to the project

D.

Update project documentation with the new scope