Due to a recent company merger, a project manager from company B has beenassigned to...

Due to a recent company merger, a project manager from company B has been

assigned to a team that is comprised of team members from company A. At the start of the

project, conflicts arise due to a lack of clarity on processes and the project manager's

relationship with company B.

What should the project manager do to resolve this conflict?

A.

Avoid the conflict as the customer feels comfortable with using processes from

company A.

B.

Review the historical information and make the decision based on the return on

investment (ROI).

C.

Ask the team to use company B's processes since they are more familiar with these

processes.

D.

Work with the team to analyze which processes are suitable to use and define them in

the ground rules.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"