PMI PMP Question Answer
An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.
Which two project events will assist the project manager to ascertain if this is the case? (Choose two)