An organization is transitioning to an agile approach.

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.

B.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.

C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.

D.

Create a record in the issue register and escalate the issue to the project steering committee.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"