An organization is transitioning to agile.

An organization is transitioning to agile. The project manager is discussing how to manage risks with the development team in light of the transition for a particular project.

The team estimates the risk level as low.

What should the project manager do?

A.

Capture all the backlog entries assessed by the development team to have evidence that risk management has been completed

B.

Create a risk register to identify, capture, review, and manage risks using a risk management process.

C.

Trust the development team's risk estimation and inform the project sponsor that the risks will be evaluated at a later time.

D.

Create a risk register and include a single generic risk, set the level to low, and then close the risk at the end of the project.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"