An ongoing project with company A is impacted by the recent acquisition of company B.

An ongoing project with company A is impacted by the recent acquisition of company B. This could affect the current suppliers for the ongoing project.

What should the project manager do next?

A.

Retain company A's supplier based on the long-term relationship with them.

B.

Consolidate the list of suppliers for companies A and B.

C.

Engage the suppliers of company B to validate the current list of suppliers.

D.

Evaluate the project suppliers of company B for future use.