An email arrives shortly after the beginning of a sprint.

An email arrives shortly after the beginning of a sprint. It is from a key project stakeholder who is unfamiliar with agile approaches and has a serious complaint about future work that has been scheduled. The stakeholder is insisting that a future work package be removed from the backlog entirely, claiming that it is unnecessary.

What should the project manager do?

A.

Address the stakeholder ' s request at the daily standup and ask for the team ' s opinion.

B.

Discuss the stakeholder ' s request at the next retrospective meeting.

C.

Invite the stakeholder to the backlog refinement meeting to discuss their request.

D.

Alter the backlog to accommodate the stakeholder ' s request.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"