An agile project team is working on an infrastructure product to be delivered incrementally over...

An agile project team is working on an infrastructure product to be delivered incrementally over several iterations. Midway through the third iteration, the whole company is

informed that the operating systems supported by the infrastructure will be terminated in the upcoming quarter. Several thousand machines will be impacted by this change.

What should the project manager do first?

A.

Prioritize the upgrade of project machines with the IT department.

B.

Inform the product owner and request more project resources.

C.

Schedule a session with stakeholders to understand the impact.

D.

Add product backlog items to prioritize operating system stories.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"