An agile facilitator has gathered a team for a new project.

An agile facilitator has gathered a team for a new project. This team and facilitator have not yet worked on a project together.

How should the facilitator proceed?

A.

Schedule a release planning session.

B.

Set up a lessons learned session from a similar project.

C.

Conduct a product roadmap session with the team.

D.

Hold a team charter discussion.