Aclient complains that an in-process multimillion-dollar project is not meeting their needs.

Aclient complains that an in-process multimillion-dollar project is not meeting their needs. The clients have consulted the project manager several times.

What should the project manager do?

A.

Review the project scope and the change management process with the client.

B.

Review the project management plan with the client to validate what is included in the project.

C.

Ask the client ' s account manager to discuss their concerns and next steps with the client.

D.

Escalate to the project committee board to review the project contract with the client.