A transformation project that is composed of agile streams has come to an end.

A transformation project that is composed of agile streams has come to an end. How should the project manager collect the experience gained during this project?

A.

Organize a lessons learned session with the team.

B.

Create a document with the information from the last sprint retrospective.

C.

Ask for feedback during the next standup meeting.

D.

Conduct a session with the members of the project steering committee.