A technician is scheduled to install internet service at the homes of three remote call center agents who have different working schedules. Their functional managers

arranged time off to allow time for installation and testing. The carrier sends an email to the project manager stating that one appointment is delayed for 2 days.

What does the project manager need to do now?

A.

Inform the relevant stakeholders.

B.

Inform the project team only.

C.

Inform the product owner.

D.

Inform the project sponsor.