A team is developing an experimental program to be used by the public.

A team is developing an experimental program to be used by the public. What should

the project manager do to ensure the desired benefits are achieved?

A.

Ensure that the project team fully tests the program.

B.

Ensure a review is done with a representative group of users.

C.

Meet with government officials to review policy requirements.

D.

Document the features fully and update the specifications.