A team is currently working on a mobile app solution.

A team is currently working on a mobile app solution. During sprint execution, one of the developers requires clarification about the acceptance criteria for a particular task

What should the project manager do to obtain the information required by the developer?

A.

Request direction from the project sponsor

B.

Write an email to the client requesting clarification

C.

Seek support from the development manager.

D.

Work with the product owner to clarify the requirement