A team has individual daily start times for each team member.

A team has individual daily start times for each team member. Sometimes the overlap between team member working hours is short. During those

times, the interactions and work as a team are reduced and ineffective.

What should the project manager do?

A.

Inform the team members who are joining late to join early and work together.

B.

Allocate the overlap time for each team member and ask them to adhere to the schedule.

C.

Ask the team to define a team charter and agree on core working hours.

D.

Ask the team to start at the same time to obtain the maximum number of team working hours.