A subject matter expert (SME) external to the project team provides a suggestion that will...

A subject matter expert (SME) external to the project team provides a suggestion that will save the project delivery time. This SME has available

time to support the project, but was not planned to be involved in the current agile iteration.

What should the project manager do?

A.

Bring the SME on board immediately and discuss the implications later.

B.

Ask the existing team members to collaborate with the SME and complete the activity.

C.

Ask the SME to complete all of the necessary changes, which will save time.

D.

Direct the team member to ignore the SME's changes as they were not planned.

PMP PDF/Engine
  • Printable Format
  • Value of Money
  • 100% Pass Assurance
  • Verified Answers
  • Researched by Industry Experts
  • Based on Real Exams Scenarios
  • 100% Real Questions
buy now PMP pdf
Get 65% Discount on All Products, Use Coupon: "ac4s65"