A software development project was recently initiated.

A software development project was recently initiated. One of the project team members is regularly questioning the project’s risk response strategy. The team member vocalizes their doubts during the daily standup meeting to share concerns regarding how the project should handle risks.

What should the project manager do first?

A.

Utilize the daily meetings to respond to the concerns.

B.

Assign each concern to the appropriate team member.

C.

Meet with the individual to understand their concerns.

D.

Escalate the team member’s concerns to the project sponsor.