A scrum master is receiving conflicting status updates for the same task.

A scrum master is receiving conflicting status updates for the same task. How should an accurate status be obtained from the team?

A.

Encourage team members to work together.

B.

Establish a clear definition of done (DoD) for each task.

C.

Assign one person to be responsible for the task.

D.

Review the deliverable carefully and determine the right status.