According to the PMP Exam Content Outline, one of the tasks under the domain of Stakeholder Management is to manage stakeholder engagement, which includes communicating and interfacing with stakeholders to meet their needs and expectations, address issues, and foster appropriate stakeholder involvement. Stakeholder engagement is the process of involving stakeholders in the project decisions and activities, and ensuring that their interests and concerns are considered and addressed. Stakeholder engagement is crucial for project success, as it can increase stakeholder satisfaction, commitment, support, and trust, as well as reduce conflicts, risks, and resistance to change12.
One of the tools and techniques for managing stakeholder engagement is the stakeholder engagement plan, which is a component of the project management plan. It describes the strategies and actions that will be used to promote productive involvement of stakeholders in decision making and project execution3. The stakeholder engagement plan should include the following elements:
Stakeholder identification and analysis: This involves identifying the key stakeholders of the project, their roles, interests, expectations, influence, and impact on the project, and their current and desired levels of engagement.
Stakeholder engagement assessment matrix: This is a table that shows the changes in the level of engagement of each stakeholder or stakeholder group over time, and the gaps between the current and desired levels of engagement.
Stakeholder engagement strategies: These are the approaches and methods that will be used to increase the level of engagement of stakeholders, such as communication, negotiation, collaboration, consultation, education, etc.
Stakeholder communication plan: This is a document that specifies the information needs and preferences of each stakeholder or stakeholder group, the frequency and mode of communication, the communication channels and methods, the communication roles and responsibilities, and the communication feedback and evaluation mechanisms.
Stakeholder engagement action plan: This is a list of specific actions and activities that will be performed to implement the stakeholder engagement strategies and the stakeholder communication plan, such as conducting meetings, workshops, surveys, interviews, presentations, reports, etc.
One of the best practices for stakeholder engagement is to set clear meeting expectations by sharing agendas in advance. This can help the project manager to obtain participation from key stakeholders who do not usually attend project meetings, by:
Showing respect for the stakeholders’ time and availability, and inviting them to attend only the meetings that are relevant and important for them.
Providing them with the purpose, objectives, topics, and outcomes of the meeting, and how their input and feedback will be valued and used.
Encouraging them to prepare for the meeting, and to raise any questions, issues, or concerns beforehand or during the meeting.
Creating a positive and collaborative atmosphere for the meeting, and facilitating the discussion and interaction among the participants.
Following up with the stakeholders after the meeting, and sharing the meeting minutes, action items, and decisions.
The other options are not correct because they do not address the root cause of the lack of stakeholder participation, which is the low level of engagement. Distributing the communications management plan may not be effective, as the stakeholders may not read it or find it relevant. Rescheduling meetings to align with the stakeholders’ availability may not be feasible, as the stakeholders may have conflicting schedules or priorities. Escalating the issue to senior management may not be appropriate, as the stakeholders may perceive it as a threat or a sign of disrespect. Therefore, the best option is to set clear meeting expectations by sharing agendas in advance, as this can increase the stakeholder engagement and participation in the project meetings. References: