A project, which has its execution phase planned m an iterative way has the following...

A project, which has its execution phase planned m an iterative way has the following metrics for the first three iterations

One of the requirements for the project states that m order to get payment authorized fcx the project neither the SPI nor the CPl can be less than 0 95 What should the project manager do in iteration 4 to ensure the project is in compliance with the requirement?

A.

Schedule crashing

B.

Fast tracking

C.

Earned schedule

D.

Earned value