A project to develop a new service is initiated by a telecommunications operator.

A project to develop a new service is initiated by a telecommunications operator. The project management plan was developed, approved, and shared with respective stakeholders. What should the project manager do next?

A.

Define deliverables, activities, and scheduling information.

B.

Estimate activity durations and list resource requirements.

C.

Incorporate the project's scope baseline in the scope statement.

D.

Start execution of the work packages according to the plan.