A project to add metro stations is being executed, with seven out of eight stations...

A project to add metro stations is being executed, with seven out of eight stations currently in place. Suddenly, a notification from the local community is received demanding the project be stopped. What should the project manager do first?

A.

Meet with project stakeholders to define a mitigation plan

B.

Register the issue and escalate it to the project sponsor

C.

Estimate the cost of changing the project location

D.

Execute the contingency plan defined in the risk management plan