PMI PMP Question Answer
A project team that is very experienced in enterprise resource planning (ERP)
systems implementation is currently planning the delivery of a new ERP project. There is a
requirement to reuse the client's security subsystem developed by a third party. The client
states that integration with the security subsystem must be done by the client's team. The
project manager does not want to have such an external dependency.
What should the project manager do first?